Z-Lab team undertook a topography surveying and mapping project, the project duration was tight and the output demands were high. All the outputs will be compared with the ultrasonic radar equipment developed by the client.

Job Description
Job Target: 1:500 topographic survey for data filing
Job Location: Chongqing, China
Job Time: Dec, 2020
Area Size: 1.84 sq.km
 
Job Demand
Accuracy Expectation: elevation 10 cm
Output Demand: point cloud, DEM
Submission Time: 2 weeks



Challenge: ravine, tower crane
Field Work
Survey Solution: Hexacopter Matrice600 Pro + SZT-R250
Number of Flight: 20 flights
Take-off Point: 5 spots
Flight Altitude: 20m – 80 m range
Strip Interval: 50 m
Data capture: 5 days (4 hours allowed to fly per day)
Flight Skyway Strips Display
Take-off                                       Landing                                    Pre-flight

Office Work

Data Processing: 7 days
Output1: geo-referenced point cloud

Output2: DEM

Checkpoint Report in TerraSolid:

root mean square 0.044 m

standard deviation 0.038 m